Before You Demolish: The Owner's Checklist

Most demolition delays are caused by items the owner controls rather than by the contractor or the City. Service disconnections, tenant notice and insurer notification all run on third-party timelines, and all three are commonly started far too late. This checklist covers what to do, in the order it should happen.

Free site visit and written quote anywhere in greater Cape Town.

Call 064 582 1436Get a demolition quote

Start immediately — these run on other people's schedules

Long-lead items outside the owner's direct control.
ItemWho does itWhy it is first
Heritage age checkOwner and contractorDetermines whether a Section 34 permit applies at all
Electricity disconnectionSupply authorityScheduled by them, not by you
Water disconnection and meter removalCity of Cape TownScheduled by them
Sewer cappingCity of Cape TownMust be capped, not merely cut
Tenant noticeOwnerStatutory and lease periods apply
Insurer notificationOwnerCover changes when a structure is demolished

A live electrical supply in a structure being demolished is the most dangerous condition on any demolition site. Disconnection is evidenced in writing before work starts. A supply that has been switched off at the board has not been disconnected.

Decide what you are keeping

Anything to be retained is identified before the soft strip, because once material is in the skip it is gone. The items owners most often regret losing are period doors and shutters, sash windows, ironmongery, cast-iron fireplaces, Oregon pine flooring, roof sheeting, garden pots and paving. Decide, mark it, and it comes out intact. See reclaimed building materials.

The full checklist

The ones people forget

Fibre and alarm contracts continue billing against a building that no longer exists, and cancelling them afterwards is harder than cancelling them before. Municipal accounts for water and refuse keep running against the property. Wildlife matters in Cape Town specifically: swifts, swallows and bats nest in roof spaces, and an occupied nest changes when the roof can be stripped.

Tenants

A tenanted property cannot be demolished around the tenancy. Demolition requires vacant possession, and getting there is a legal process with its own timeline that sits entirely ahead of the demolition programme.

Where the position is contested, it is a matter for an attorney rather than for a demolition contractor, and the programme waits on it. Building a demolition schedule around an assumption that a tenant will leave on the notice date is a common and expensive error.

Insurance: what changes the day the structure goes

An insured building that no longer exists is an insured risk that has changed fundamentally, and an unnotified demolition can void cover on both the structure and the site. Four conversations happen with the insurer before work starts.

Insurance positions to confirm before demolition.
QuestionWhy it matters
Is cover maintained during the works?The site still carries liability toward the public and neighbours
What happens to structure cover?Premiums on a demolished building are money spent on nothing
Is the vacant site covered?Vacant land carries different terms to an occupied property
Does the contractor's liability cover suffice?Ask for the schedule, not a summary

See demolition insurance and liability for what to verify on the contractor's side.

Clearing the building properly

A building being demolished contains more that matters than people expect, and the soft strip is not the moment to discover it. Work through the property room by room before the crew arrives.

  1. Documents. Title deeds, approved plans, guarantees, service records — frequently in a roof space or a garage cupboard.
  2. Anything sentimental or irreplaceable. Once it is in a skip it is gone.
  3. Valuables and metals. Copper cylinders, brass fittings and lead flashings walk off unsecured demolition sites.
  4. Appliances and geysers. Worth removing intact if they are being reused.
  5. The garden. Pots, established plants worth lifting, garden lighting, irrigation controllers, and anything the machine route will destroy.
  6. Meters and keys. Final readings recorded, keys accounted for.

Pets and wildlife

Pets move off the property for the duration rather than being shut in a room, because a demolition site has open access, machinery movement and unfamiliar noise. Cats in particular return to a demolished house and need to be relocated properly rather than simply kept indoors on the day.

Wildlife is a specifically Cape Town consideration. Roof spaces here host swifts, swallows and bats, and honeybee colonies establish inside cavity walls and chimneys with some regularity. Bats are protected, and an active bat roost requires specialist advice before the roof is opened. A bee colony needs a removal specialist rather than a demolition crew — disturbing one mid-demolition puts the whole site at risk. Both are checked during the site survey.

The week before

Confirm the disconnections have actually happened rather than merely been requested. Move the pets. Take the final meter readings. Walk the property once more for anything missed, particularly in the roof space and the garage. Tell the neighbours the start date. Park vehicles away from the haul route.

Frequently asked questions

What do I need to do before demolition starts?

Establish the build date for the heritage check, request electricity, water and sewer disconnection in writing, give tenants proper notice, notify your insurer, agree any party wall standard in writing, photograph neighbouring structures, and mark everything you intend to keep before the soft strip begins.

Who disconnects the electricity before demolition?

The supply authority disconnects and removes the connection, and it is scheduled on their timeline rather than yours. Switching a supply off at the distribution board is not disconnection. Written proof of disconnection forms part of the permit file, and a live supply in a structure being demolished is the most dangerous condition on any site.

Do I need to tell my insurer about a demolition?

Yes. Cover on a property changes materially when a structure is demolished, and an unnotified demolition can void cover on both the structure and the site. Notification also matters for liability toward neighbouring property during the works.

Can I keep materials from the building?

Yes, where they are identified before the soft strip. Period doors, shutters, sash windows, ironmongery, cast-iron fireplaces, Oregon pine flooring and roof sheeting are the items owners most often want back. Mark them at the site visit and they come out intact rather than into the skip.

What about birds or bats nesting in the roof?

Roof spaces in Cape Town commonly host swifts, swallows and bats, and an occupied nest changes when the roof can be stripped. The roof space is checked during the site survey. Bats in particular are protected, and their presence requires specialist advice before the roof is opened.